Judge refuses to toss lawsuit over 1.25 miles of Richmond railroad alleged to be at risk for derailments

RICHMOND — The largest freight railroad company in the nation may have lost its bid to toss out a lawsuit alleging its 1¼-mile Richmond Rail Connector project was improperly built nearly a decade ago and continues to damage a small business nearby.

A Contra Costa County Superior Court judge has tentatively denied a slew of motions — filed by the BNSF Railway Company and a construction engineering consultant — that sought dismissal of the case this week.

BNSF had argued that the suit could seek removal of the track in question, which would be a matter of federal jurisdiction, but Judge John Levine said there is no admissible evidence the plaintiff is asking to shut down.

As a result, the jury trial slated to begin next week was delayed following a hearing Monday — the latest roadblock in an arduous legal battle that’s slogged through the courts for more than seven years.

The case revolves around the Richmond Rail Connector, a $22.6 million Caltrans-approved plan that BNSF and government officials started work on in 2013 to design, rehabilitate and construct 1.25 miles of curved track to transport crude oil and other cargo destined for the Port of Oakland.

But, BNSF and its contractors appear to have overlooked staggering issues during the connector’s construction and maintenance, according to a complaint filed in August 2017 by the property’s owner, Albert Engel Sr.

His amended complaint alleges breach of contract, negligence, specific performance and more regarding the mostly publicly funded Richmond Rail Connector project, which was completed in 2015 and sits less than a mile inland from the city’s marshy shoreline.

As his complaint has slogged through Contra Costa County’s courts, a host of records his legal team gleaned from railroad staff, contractors and scientific experts has allegedly stoked concerns that the connector could spell disaster for Richmond’s shoreline and the entire East Bay.

Engel’s attorneys allege that an unlicensed surveyor conducted all pre-design and pre-construction surveys, BNSF reneged on contractual responsibilities to preserve adequate, unobstructed drainage facilities, and construction crews took shortcuts to meet deadlines associated with the project’s public grant funding.

Engel’s lawsuit alleges that lax construction standards and poor track maintenance has led to overgrown vegetation, homeless encampments and pools of water that at times accumulate around the nearly decade-old berm — problems that he said he fears could potentially foreshadow a train derailment along that track.

BNSF’s lead attorney, Colette Stone, argued on Monday that Engel’s legal team may ultimately advocate for removing the entire rail line during the upcoming jury trial. Stone proposed that the case should be tossed out because state courts are unable to rule on the regulation of railroads, including issues of permitting, construction, and operation.

That remedy, however, has not been requested in any of Engel’s court filings. Instead, his complaint, as it currently stands, is seeking damages.

FOLLOW US ON GOOGLE NEWS

Read original article here

Denial of responsibility! Todays Chronic is an automatic aggregator of the all world’s media. In each content, the hyperlink to the primary source is specified. All trademarks belong to their rightful owners, all materials to their authors. If you are the owner of the content and do not want us to publish your materials, please contact us by email – todayschronic.com. The content will be deleted within 24 hours.