Once Highway 1 stabilized at Rocky Creek, traffic can return to Big Sur

SALINAS – Work on the Rocky Creek slip-out of Highway 1 continues to be focused on stabilizing the edge of the roadway because once that is done a temporary signal system will be installed, opening up the roadway to unrestricted traffic under one-way traffic control and providing vital visitor and business flow to the Big Sur area.

When the edge stabilization work will be complete should be determined sometime later this week, according to Caltrans.

But with rain in the forecast for Saturday, Caltrans will be suspending the twice-daily convoys to and from the Big Sur area restricted to locals and essential workers only. That information was made available at the County of Monterey news briefing on Wednesday.

RELATED: Big Sur Marathon: Changes to the course approved, race set for April 28

“The last convoys will continue 7 a.m.-5 p.m. Wednesday, Thursday and Friday, but we’re canceling the Saturday convoys,” said Kevin Drabinski, Caltrans District 5 spokesman. “There’s an expectation that the convoys will resume at 7 a.m. on Sunday, but we’re going to wait until we get an update from the National Weather Service this Friday morning to confirm the feasibility for the Sunday resumption of convoys.”

Work on the slip-out which occurred March 30 includes Caltrans’ conducting vital geotech assessments which have allowed the convoys and implementing a traffic management system for the corridor including signage advising of the closures on Highway 1.

“On the northbound shoulder area we went in and created a little extra room,” explained Drabinski. “We improved the drainage on the northbound shoulder and also widened the shoulder to give the northbound lane a little extra room.”

K-rail, the concrete barriers placed along the center line to help channelize the convoy passage, have been installed. Caltrans has also developed and completed design and construction details for the stabilization for the edge of the roadway.

That’s been the focus since day one. Developing a design, and finalizing the construction details, said Drabinski. Now Caltrans has been able to engage a contractor who has mobilized to the site.

“We hope later this week to release an estimate of when that edge stabilization work will be complete, that will be an important milestone for everyone,” he stressed.

Work by contracted crews began Tuesday with drilling, installing and grouting 25-foot vertical rock dowels through the southbound lane toward the west edge of the roadway pavement.

Drabinski said it is the first step of stabilizing the edge and said Caltrans should have equipment on site by Thursday that will allow going to the next phase of stabilization.

“That is a little bit more adventurous work in which they’ll repeat the drilling of these essentially inch-and-a-quarter rebar dowels horizontally, so reaching out over the edge of the pavement and then having crew members drill through the entire run of the failure area,” Drabinski said. “Then they’ll install reinforced shotcrete on the vertical face of the repair. Hanging off the edge and drilling is going to take a little longer than the vertical drilling right in the roadway.”

Zeke Dellamas, Caltrans emergency manager, said shotcrete is concrete that is sprayed on, manually applied by a worker from a crane, that sticks to the vertical face of the slip-out. It reinforces and connects to different bolts that have been applied horizontally to help distribute the load to the rock bolts that are used in the stabilization effort.

FOLLOW US ON GOOGLE NEWS

Read original article here

Denial of responsibility! Todays Chronic is an automatic aggregator of the all world’s media. In each content, the hyperlink to the primary source is specified. All trademarks belong to their rightful owners, all materials to their authors. If you are the owner of the content and do not want us to publish your materials, please contact us by email – todayschronic.com. The content will be deleted within 24 hours.

Leave a Comment