PG&E says electricity plan can boost South Bay innovation and economy

SAN JOSE — PG&E said Wednesday it is pushing to bolster Silicon Valley’s economy and innovation future, including by undertaking major electricity projects in the South Bay and East Bay.

Executives with the utility appeared at a breakfast in downtown San Jose sponsored by law firm Hoge Fenton, assuring business leaders who gathered for the event that the company was doing all it can to improve the reliability of its services.

A 9.8-acre vacant land site near the corner of Coleman Avenue and Santa Teresa Street in downtown San Jose. PG&E San Jose Substation B is located in the background.(George Avalos/Bay Area News Group)
PG&E substation in downtown San Jose, visible in the background next to an empty plot of land totaling 9.8 acres near the corner of Coleman Avenue and Santa Teresa Street, May 2023. (George Avalos/Bay Area News Group)

“We have a long way to go but we are working very diligently to deliver reliable energy,” Teresa Alvarado, PG&E’s South Bay & Central Coast regional vice president, said at the event, which was held at the Silicon Valley Capital Club on East San Fernando Street.

Oakland-based PG&E detailed two mega projects being crafted by a Midwest power company to bring big chunks of electricity into North San Jose and downtown San Jose.

PG&E hopes the projects will help ensure that a lack of reliable electricity doesn’t hobble economic expansion in these sections of Silicon Valley.

“We are trying to get ahead of the load growth in this area,” said James Tuccillo, a PG&E distribution engineering manager who was part of a utility company panel at the Hoge Fenton event.

LS Power Grid California, an affiliate of Missouri-based LS Power, is leading the effort to develop two major new electricity facilities in the Bay Area.

Here are the details of each project, according to LS Power Grid California:

— Metcalf Substation to San Jose B Substation. This project would connect a new terminal near the existing Metcalf station in South San Jose to a new terminal in downtown San Jose near the corner of Coleman Avenue and Santa Teresa Street. The project includes underground transmission lines connecting the two terminals as well as the existing electrical grid. LS calls this the Power Santa Clara Valley Project.

— Newark Substation to Northern Receiving Station. This project would connect a new terminal near the PG&E Newark Substation in Fremont to Silicon Valley Power’s Northern Receiving Station in Santa Clara via a new terminal near the Regional Wastewater Facility in Alviso. The project includes mostly underground transmission lines connecting the terminals to each other and the existing electrical grid. LS calls this the Power the South Bay Project.

Both projects should begin construction in early 2026 and go into service in 2028.

The proposals are being touted at a time when PG&E is under fire for skyrocketing monthly utility bills that have soared far faster than the overall inflation rate in the Bay Area as measured by the costly region’s consumer price index.

Over the one-year period that ended in January 2024, combined bills for a typical residential customer who receives both electricity and gas services from PG&E averaged roughly $294.50 a month.

That was a 22.3% increase over the average monthly bill in January 2023. In sharp contrast, the Bay Area inflation rate rose 2.6% during 2023.

PG&E also remains under scrutiny in the wake of a decade of PG&E-sparked disasters that included a fatal gas explosion that destroyed a San Bruno neighborhood as well as a string of infernos that torched huge swaths of land in the North Bay wine country and other sections of Northern California.

“We all know about the disastrous wildfires caused by PG&E equipment torching vegetation that is very dry,” Alvarado said during the event.

PG&E officials during the event stated that in 2023 the utility reduced its wildfire risk by 96%, but they did not explain how they arrived at that figure.

The efforts by PG&E to support major energy projects in the region might be an instance of the utility scrambling to ensure that it is the entity poised to deliver power into Silicon Valley, in the view of Kelly Snider, a professor in San Jose State University’s Department of Urban and Regional Planning who was in attendance at the Hoge Fenton event.

FOLLOW US ON GOOGLE NEWS

Read original article here

Denial of responsibility! Todays Chronic is an automatic aggregator of the all world’s media. In each content, the hyperlink to the primary source is specified. All trademarks belong to their rightful owners, all materials to their authors. If you are the owner of the content and do not want us to publish your materials, please contact us by email – todayschronic.com. The content will be deleted within 24 hours.